High School Renovation: Project Update
The following report was released by the School District’s Owner Representative on May 29, 2013.
Lake County High School Construction Project Subcontractor Bid Dates Announced.
The Lake County High School Renovation and Addition project has been moving ahead over the past several months. The design is being finalized and the project’s general contractor, Adolfson & Peterson Construction, has provided the following preliminary information for subcontractors to be aware of regarding bidding dates:
May 2013:
- 5/29/2013 – Structural Steel, Mechanical / Electrical Design-Assist RFPs issued.
- 5/30/2013 – Fire Suppression Design / Build proposals due.
June 2013:
- 6/11/2013 – Steel and MEP RFP responses due.
July 2013:
- 7/17/2013 – Bid Package #1 issued (Earthwork, Utilities, Foundations, Concrete, Waterproofing).
- 7/25/2013 – Bid Package #1 bids due.
- 7/26/2013 – Bid Package #1 finalized Construction Documents issued.
- 7/29/2013 – Competitive subcontractors for Bid Package #1 to confirm pricing based on Construction Documents.
- 7/30/2013 – Progress set issued (Auditorium Seating, Roofing, Theatrical Rigging, Drywall/Framing, Storefront/Glazing, Siding).
August 2013:
- 8/9/2013 – Progress set bids due for trades listed above.
- 8/23/2013 – Final bid package issued (All remaining trades).
September 2013:
- 9/5/2013 – All remaining bids are due.
Construction work will begin this summer and the project is slated for completion for the 2014/2015 school year. Lake County community members with any questions regarding the high school project may contact the Lake County School District’s Owner’s Representative for the project, Consilium Partners, at LCHS@consiliumpartnersllc.com.
And now in Spanish:
Fechas Anunciadas para el ofrecimiento de servicios (bids) como sub-contratista del Proyecto de Construcción de la Escuela Preparatoria del Condado Lake.
El Proyecto de Adición y Renovación de la Escuela Preparatoria del Condado Lake, ha avanzado en algunos meses atrás. Los diseños están siendo terminados y el contratista general del proyecto, Constructora Adolfson & Peterson, ha dado la siguiente información preliminar para que los sub-contratistas tengan conocimiento de las fechas concernientes al ofrecimiento de servicios:
LCHS students review design ideas at the February Design Charrette. Community input was incorporated into the concept which was revealed April 9. The construction phase is ramping up this summer.Mayo, 2013:
- 05/29/2013 – Estructura de Acero, Emisión del Diseño-Colaboración RFPs para lo Eléctrico/ Mecánico.
- 05/30/2013 – Diseño de Supresión de Fuego/Límite de Propuestas de Construcción.
Junio, 2013:
- 06/11/2013 – Límite para Respuestas de MEP RFP y Acero.
Julio, 2013:
- 07/17/2013 – Paquete de Ofrecimientos Emitidos #1 (Trabajo de la tierra, Servicios Públicos, Cimientos, Concreto, Prueba de Agua).
- 07/25/2013 – Límite de paquete de ofrecimientos #1.
- 07/26/2013 – Paquete de ofrecimientos #1 Emisión de documentos de Construcción finalizada.
- 07/29/2013 – Sub-contratistas nominados para el Paquete de Ofrecimientos #1 Confirmando precios basados en los Documentos de la Construcción.
- 07/30/2013 – Distribución del Arreglo del Progreso (Asientos del Auditorio, Techo, arreglos del escenario, tabla-roca/estructuras, fachada, cambio de vidrios, exterior del edificio).
Agosto, 2013:
- 08/09/2013 – La fecha límite del ofrecimiento de servicios para la construcción está enlistada arriba.
- 08/23/2013 – Emisión final del paquete de ofrecimiento del servicio (todos los ofrecimientos que permanezcan).
Septiembre, 2013:
- 09/05/2013 – Todos los ofrecimientos de servicios que queden, tienen que ser entregados.
El trabajo de construcción comenzará este verano y el proyecto elegido, será terminado para el año escolar 2014-2015. Los miembros de la comunidad del Condado Lake que tengan preguntas concernientes al proyecto de la escuela preparatoria, pueden contactar al Representante del Proyecto, propietario que es el Distrito Escolar del Condado Lake, Colaboradores del Consejo a la siguiente dirección de e-mail: LCHS@consiliumpartnersllc.com